Bicycle Transportation Plan(src: 2016 Bicycle Transportation Plan)

Adding 14.73 Miles more Bike way
| 7 Complete | |
| 6 Construction | |
| 5 Bidding | |
| 4 Design | |
| 3 PreDesign | |
| 2 Feasibility | |
| 1 Programmed |
| 7 Complete | |
| 6 Construction | |
| 5 Bidding | |
| 4 Design | |
| 3 PreDesign | |
| 2 Feasibility | |
| 1 Programmed |
Buffered bike lane provides extra separation from automobiles
| 7 Complete | |
| 6 Construction | |
| 5 Bidding | |
| 4 Design | |
| 3 PreDesign | |
| 2 Feasibility | |
| 1 Programmed |
A subset of Class III bike routes that include traffic calming features, such as:
| 7 Complete | |
| 6 Construction | |
| 5 Bidding | |
| 4 Design | |
| 3 PreDesign | |
| 2 Feasibility | |
| 1 Programmed |
| 7 Complete | |
| 6 Construction | |
| 5 Bidding | |
| 4 Design | |
| 3 PreDesign | |
| 2 Feasibility | |
| 1 Programmed |





| Street | Bikeway Class |
|---|---|
| McClellan Rd | Class IV |
| Stelling Rd | Class IV |
| Rainbow Dr | Class II |
| Historic De Anza Trail | Class I |
| Stevens Creek BLVD | Class IV |
| Tamien Trail | Class I |
| Vallco Pkwy | Class II Buffered |
| Main Street | |
| Finch Ave | Class IV |
| Calle De Barcelona | Class III BLVD |
| Creekside Park | |
| Regnart Creek Trail | Class I |
| Pacifica Dr | Class III & Class II |
Spot improvements are designed to address locations where there are specific biking challenges
| 7 Complete | |
| 6 Construction | |
| 5 Bidding | |
| 4 Design | |
| 3 PreDesign | |
| 2 Feasibility | |
| 1 Programmed |
(src: 2018 Pedestrian Transportation Plan)

Improve Safety, Accessibility, and Connectivity
| 7 Complete | |
| 6 Construction | |
| 5 Bidding | |
| 4 Design | |
| 3 PreDesign | |
| 2 Feasibility | |
| 1 Programmed |
Spot improvements are designed to address locations where there are specific pedestrian connectivity challenges
| 7 Complete | |
| 6 Construction | |
| 5 Bidding | |
| 4 Design | |
| 3 PreDesign | |
| 2 Feasibility | |
| 1 Programmed |